| PPPL Engineering Procedures | ||
| Topic | Number | Full Title |
| MANAGEMENT | ||
| Roles + Responsibilties | ENG-057 | Project and Governance Roles and Responsibilities |
| Project Execution Plans | ENG-020 | Project Execution Plan |
| Job Cost Estimating (WAF) | ENG-053 | Job Cost Estimate Development & Review |
| Project Status Review Board (PSRB) | ENG-049 | Project Status and Oversight |
| System Breakdown Structure + Risk | ENG-063 | System Breakdown Structure and Categorization |
| Work Planning | ENG-032 | Work Planning Procedure |
| Document + Record Numbering | ENG-061 | Engineering Design Document and Record Numbering |
| Davis-Bacon | ENG-058 | Davis-Bacon Screening |
| DESIGN | ||
| Requirements | ENG-050 | Job Requirements Documentation and Control |
| Design Reviews + Calculations | ENG-033 | Design Verification |
| PPPL Engineering Standards | ENG-019 | PPPL Engineering Standards |
| FMEA Guidelines | ENG-008 | Failure Modes and Effects Analysis |
| RAMI Guidelines | ENG-007 | Reliability, Availability, and Maintainability (RAM) Modeling and Apportionment |
| DOCUMENTATION | ||
| Drawings | ENG-010 | Control of Drawings |
| Specifications | ENG-006 | Preparation, Review & Approval of Technical Specifications |
| Statements of Work | ENG-060 | Preparation, Review & Approval of Statements of Work |
| OPERATIONS | ||
| Test Plans | ENG-062 | Plannning and Performing Tests |
| Procedures | ENG-030 | PPPL Technical Procedures |
| Conduct of Operations | ENG-055 | Conduct of Operations |
| Interlock Key Control | ENG-011 | Interlock Key Control |
| T-Mods | ENG-036 | Control of Temporary Modifications |
| Pressure Testing | ENG-014 | Hydrostatic and Pneumatic Testing |
| Equipment Calibration | ENG-002 | Control of Measuring Test Equipment and Calibration |
| Power Outage Nofication | ENG-022 | Scheduled Site Power Outage Notification |
| Electrical Load Reduction | ENG-009 | Electric Service Load Reduction |
| Preventative Maintenance | ENG-016 | PPPL Preventive Maintenance Program |
| FABRICATION | ||
| Travelers | ENG-059 | Process Plan/Traveler for PPPL Built Components |
| Identification + Control of Items | ENG-012 | Identification & Control of Items |
| Shop Safety | ENG-048 | Machine/Carpenter Shop Equipment Safety Checklists |
| Welding + Brazing | ENG-037 | General Welding and Brazing Requirements |
| Welding Materials | ENG-038 | Welding Materials Control |
| COMPUTING | ||
| Cybersecurity Incident Response | ENG-034 | Cyber Security Incident Response |
| TRAINING | ||
| Electrician Qualification | ENG-041 | Electrician Qualification |
| Boiler Operator Qualification | ENG-042 | Boiler Operator Qualification |
| Carpenter Qualification | ENG-043 | Carpenter Qualification |
| HVAC Mechanic Qualification | ENG-044 | HVAC Mechanic Qualification |
| Machinist Qualification | ENG-045 | Apprentice Machinist and Qualified Machinist Qualification |
| Metal Fabricator Qualification | ENG-046 | Metal Fabricator Qualification |
| Facilities Tech Qualification | ENG-047 | Facilities Technician Qualification |
| FACILITIES + CONSTRUCTION | ||
| Facilities Mission | ENG-051 | Facilities and Infrastructure Mission Readiness |
| OPEX Projects | ENG-052 | Operating Expense (OPEX) Projects Prioritization and Administration |
| GPP Projects | ENG-005 | General Plant Projects Administration |
| Computer Center Work Control | ENG-039 | Computer Center Work Control |
| Electrical Equipment Approval | ENG-023 | Electrical Equipment Approval |
| Hoisting + Rigging + Lifting + Vechicle | ENG-021 | Program for Hoisting & Rigging, Forklifts, Manlifts, Special Purpose Vehicles, Utility Vehicles and Portable Equipment |
| Digging | ENG-024 | Digging Permits |
| FIRE SAFETY | ||
| Fire and Life Safety Systems | ENG-026 | Fire and Life Safety Systems |
| Fire Dampers + Doors | ENG-025 | Impairments of Fire Dampers and Fire Doors |